CURRENT STAGE OF WORKS:
Date: 6/07/2026 – 17/07/2026
Work Overview: Building 4 South nearing handback
What happened on site last week?
Building 4 South
Works have been completed, marking the completion of the current scope in this area.
Balconies will be progressively handed back to residents once they can be safely accessed and all final checks have been completed.
The completion of these works represents a significant milestone for the project.
Building 4 North and Building 3 South
Demolition of the existing render surrounding the door openings was completed.
Reglets were cut in preparation for the next stage of waterproofing and façade remediation works.
Building 1 and Building 4 West
Works are currently awaiting further design details to allow construction activities to progress.
Building 1 North
Measurements were completed for the installation of the new balustrades.
What is happening on site this week?
Building 4 South
Balcony scaffold removal is scheduled to commence following the completion of the external works.
Building 4 North and Building 3 South
Brickwork repairs and reinstatement works are programmed to commence.
Building 1 North
Rendering and tiling works will continue as part of the ongoing external façade remediation works.
ADDITIONAL WORKS NOTICES:
Fly screens have also now been installed to Buildings 2, 3, and 4.
We request that residents do not open or adjust the newly installed fly screens, as they must remain in their set position until internal repair works are completed. Glass sliding doors can be opened outside of site working times but access to the balcony is not permitted at this stage.
Site Reminder: Strictly no access is permitted to active work areas during the current construction and remediation works.
These restrictions are in place to ensure compliance with Work Health and Safety (WHS) requirements and to protect all residents, visitors, and workers on site.
In addition, certain works currently underway, such as waterproofing applications and curing processes, are highly sensitive. Any foot traffic or interference may:
Compromise the integrity of the works
Cause defects or failures in waterproofing systems
Result in delays and the need for rework
We kindly request that all residents:
Do not enter barricaded or designated work zones
Follow all posted signage and directions from site personnel
Do not walk through on or through any area currently in construction
Residents are reminded to keep all items off their baclonies while works asre occurring. If your balcony is currently being worked on, please remove all items from balconies. Items such as pot plants and outdoor furniture placed directly on waterproofed surfaces can cause damage and may result in the works not meeting compliance requirements. Once items can be returned to balconies, we will issue a notice so residents can place items on the completed surface
Your cooperation is essential in maintaining a safe environment and ensuring the works are completed efficiently and to the required standard. Thank you for your understanding and cooperation.
To stay informed and receive the latest updates on the works being carried out Strathview: 23 George Street, North Strathfield, we encourage you to join the Izzat Strathview communication channel – click here to join:
https://tinyurl.com/StrathviewComm
Frequently Asked Questions
Q: How long is the phase that involves my unit?
Buildings 2 and 3 are scheduled between May 2025 and November 2025. Buildings 1 and 4 are scheduled between September 2025 and July 2026. Buildings 1 and 4 will take longer due to the amount of balconies and entry ways in this area. Please note that the dates provided do not account for inclement weather conditions that delay construction but the builders will be working hard to maintain the dates as much as possible. The project is anticipated to be completed and site handed back in September 2026.
Q: Do we just lose the courtyard and/or balcony for our stage or the duration of the works?
You will not have access to the courtyard and/or balcony for the duration of the remediation works for the stage that your unit is in. While we empathise with residents on this impact, unfortunately due to safety reasons, access can not be provided.
Q: Will work only happen externally?
While works are external, all interior items that are unfixed need to be moved 1m away from the courtyard and/or balcony doors to ensure access to install the protective covering. This includes curtains and blinds. This is to ensure all personal items are undamaged.
Q: Are we expected to remove all furniture from the balcony and relocate it?
Yes, it is the resident’s responsibility to ensure that all furniture, plants and other items from their balconies are removed prior to the dates where access is required for Renfay to undertake the remedial works in their stage of works.
Q: Will work affect all balconies of my unit or only a certain side?
The works will affect all balconies on the ground floor. All windows and doors will need to remain locked when the protective covering is not in place to ensure compliance with WHS.
If you have two balconies in your home on the ground floor, please note that work will only occur on one balcony at any given time. Renfay’s schedule will clearly indicate the areas that will be impacted. Have a look at the Notice of Demolition on the right side of this page to check the current work areas.
Q: What is the protective covering and what will it impact?
The protective coating is to allow the door and glazing suite to be removed so the new waterproofing membrane can be installed under the door. This will mean that there will be limited natural light and ventilation coming from your balcony doors during the works.
Once this is completed, the door will be reinstated, and the temporary protection will be removed. Access to the courtyard and/or balcony and opening of the door will be restricted for the length of works on the stage of works in which your unit is in.
While we empathise with residents during the period of construction, an alternative is not suitable as this is required to fulfill WHS obligations under the WHS Act and Regulation. Should the protective covering be altered in any way, it would pose significant WHS risks for all parties involved.
If you have children or pets, please let us know via the Communication Channel https://tinyurl.com/StrathviewComm or email us at strathviewproject@izzat.com.au so we can ensure additional measures are taken to secure the area for safety precautions.
Q: How long will the protective covering be on?
Each door to the courtyard and/or balcony will have a temporary hoarding/protection installed for approximately 10 days.
Q: When will we be able to open the doors again?
You will be able to open the doors to the ground floor courtyard and/or balcony once the phase is completed.
For WHS reasons, all ground floor doors within the current work zones must remain locked. This is to mitigate any potential risks, especially concerning children and pets on site. While doors will be locked, you will still have access to windows, which you are welcome to open outside of Renfay’s work hours and on rain days when works are not occurring on site.
This is just for the ground floor homes in the current work zone.
Q: How long will the doors be off?
The doors will be off for approximately 2 weeks.
Q: Will I need to provide access through my apartment during any stage of these works?
Renfay will access the unit from the courtyard and/or balcony for installing the protective covering and door removal. Doors will need to be left unlocked when they are removed. Renfay will also need access for any make good works. You are more than welcome to be home while these works are undertaken.
Q: What time will the works be?
The majority of building works will occur during standard working hours (7am to 5pm, Monday to Friday). Selected trade personnel are well experienced in working within live environments and will be trained to have the highest regard for tenants and the general public to ensure their safety throughout the project.
Occasionally Renfay will be required to work Saturdays 8am to 4pm.
Q: Is smoking or vaping allowed on site?
The site strictly prohibits smoking and vaping. Smoking and vaping are only permitted at the designed location offsite. This is reiterated in the tool box talks.
Q: Do the builders clean the site?
They sure do! The team will keep the site in a tidy condition to ensure cleanliness and to maintain safety and WHS.
Have a question and can’t find your answer? No problem! Just email us at strathviewproject@izzat.com.au and we will be happy to help.